Stewart Park Phase II: grant agreement and final design work
Outcome: Council approved both actions. Staff reported that Phase I construction had restarted, Phase II advertising was anticipated for late September 2026, and Phase I completion was anticipated around March 2027.
Why it matters: These were implementation steps, not merely another conceptual discussion. Approval preserved the grant framework and moved the project closer to construction bidding and delivery.
The two items should be read together: one secures the funding framework, while the other advances the professional design work needed to build the project.
- What is the complete Phase II budget after grant and local funding are combined?
- What remains before a construction contract can be awarded?
- What schedule and grant deadlines govern the next steps?