Pennsylvania Avenue Grade Separation
Outcome: Council voted 5–0 to withdraw the Pennsylvania Avenue Grade Separation from the 2024 TCEP cycle and reapply in 2026. Project development continues while the City seeks a later allocation year and additional funding.
Key points
- The decision changes the funding strategy; it does not stop the project.
- Design is approximately 65% complete.
- The total project estimate is approximately $147.6 million.
- Federal grant applications and other funding opportunities remain pending.
Fiscal impact
No construction appropriation was approved. The packet’s approximately $54.7 million gap included the withdrawn $49.4 million award; staff described an approximately $110 million funding need without that award.
What to watch
- Why staff believes withdrawal is less risky than keeping the current award.
- What amount and schedule are anticipated for the 2026 TCEP application.
- How drainage, Union Pacific, Caltrans and utility dependencies affect the revised schedule.